How do you replace 540 feet of sewer under a popular golf course without interruption to golfers, utility customers or street traffic?That was the question when part of an Eagle, Idaho, wastewater main, which ran beneath a fairway of the famous BanBury Golf Course, required upsizing. Upsizing 8-inch PVC pipe to 12-inch HDPE appeared as though it couldn’t be done via pipe bursting. The existing pipe lay at 19 feet in a pipe-chip bed of crushed rock in sandy, cobbly dirt. The combination does not displace easily, which made pipe bursting that much more difficult. Additionally, water was a constant
Case Study: Pipe bursting allows upsizing with minimal disruption
Mar 09, 2015
| by Craig Mandli |